Updated Electricity Costs for Industries Above ۱ MW

With the aim of ensuring the proper implementation of Cabinet Resolution No. 94395/T60027H, dated September 2, 2022, a new approach to the electricity distribution and tariff-setting system has been announced. This directive, rooted in Article 16 of the Knowledge-Based Production Leap Law, seeks to optimize the energy mix of industrial facilities and reduce reliance on fossil fuels for electricity generation. The following sections outline the details of this national initiative for industrial managers.

1. Scope and Eligible Industries

This regulation specifically requires all industrial units with an authorized power capacity exceeding one megawatt (1 MW) to change their electricity procurement methods. Accordingly, companies operating in industrial parks and large manufacturing complexes must develop precise plans to manage their electricity consumption.

It should be noted that, under the explicit provisions of the law, tourism facilities and hotels are exempt from these tariffs, and their electricity rates will continue to be calculated under the previous regulations.

2. Gradual Increase in the Renewable Energy Share

According to the government’s medium-term plan, in 2023, one percent (1%) of the annual electricity consumption of industries covered by this regulation must be supplied from renewable sources.

This percentage is not fixed. To further encourage the transition to clean energy, the required share increases by one percentage point each year from 2024 through 2027. Accordingly, industries must be prepared to supply five percent (5%) of their electricity consumption from renewable sources by 2027 to avoid penalties arising from differences in electricity tariffs.

3. Three Methods of Procuring Renewable Electricity

Industrial units can fulfill their clean energy obligations through three operational approaches:

  • Self-generation: Constructing solar or wind power plants within the industrial facility’s premises to generate electricity directly.

  • Energy Exchange: Purchasing renewable electricity energy or capacity certificates through the Green Board of the Iran Energy Exchange.

  • Bilateral Contracts: Entering into direct agreements with private-sector investors involved in renewable electricity generation.

Important Note: If an industrial unit fails to procure its designated share of electricity through the above methods, Tavanir is required to include the cost of the shortfall in the final electricity bill, based on renewable energy tariffs, which are considerably higher than subsidized electricity rates.

4. Financial Calculations and Tariff Announcements

The calculation of electricity bills under this scheme is structured as follows: a portion of consumption is billed at the standard rate, while the regulated portion (1% to 5%) is calculated based on the new tariffs.

For industries that procure their electricity through the Second Board of the Iran Energy Exchange, calculations are carried out in accordance with the applicable Energy Exchange regulations.

Furthermore, SATBA (Renewable Energy and Energy Efficiency Organization) is responsible for continuously monitoring the market, updating the average electricity purchase price from renewable power plants every two months, and notifying Tavanir of the revised rates for application to electricity bills.

5. Incentives and Management of Surplus Generation

The government offers special incentives to industries that generate more renewable electricity than their legally required share.

If a facility’s green electricity generation exceeds its required consumption quota, the facility owner may either:

  • Bank the surplus electricity for up to one year and use it during high-consumption periods, such as the summer peak season.

  • Earn revenue by selling the surplus electricity in accordance with SATBA protocols.

6. Technical Standards for Grid Connection and Metering

To prevent interference with the national electricity grid, the installation of smart meters and accurate metering equipment is mandatory. These devices must be accessible to and monitored by the grid operator (the distribution company or regional electricity company).

The equipment must separately record the amount of electricity generated by the solar power plant and the amount drawn from the public electricity grid.

If technical limitations prevent separate metering, the industrial unit is required to connect its power plant directly to the public electricity grid substations.

Conclusion and Future Outlook

The implementation of this resolution represents a fundamental shift in the electricity consumption model of Iran’s industrial sector.

Although it may involve initial investment costs in the short term, it is expected to contribute to the long-term stability of the country’s electricity grid and reduce unexpected power outages during the hot season.

By implementing this regulation, Iran’s industrial sector will move closer to international standards while strengthening its ability to secure a reliable and sustainable electricity supply.